2023 – Brick Repairs ($190,000)
This project was completed for Homestead – Property Standards & Construction. The scope included dismantling and rebuilding 5 buttresses, brick replacement within the wall and mortar joint chip and repointing. Full pedestrian protection was erected along the sidewalk and the work was completed off a swing stage, which was relocated as work progressed.
This project consisted of chipping and repointing deteriorated mortar joints replacement of deteriorated cap stones, installation of stainless steel drip flashings and installation of new caulking. All access was completed via aerial work platform.
This was a design build project with the City of Kingston. Morey worked with their engineer to produce a constructable design. The challenge was working around the existing high voltage transformer which was not feasible to move with the citys budget. The scope included the dismantle and removal of existing retaining wall and accessible ramp.
Morey also reconstructed the retaining wall with geotextile tie backs as per engineered drawings, and poured a new concrete accessible ramp with tactile wanring strips. Finally the existing railing was salvaged and reinstalled.
This project included chipping and repointing of historic carins, as well as the removal and reset of stones where required. Morey completed the project in accordance to Parks Canada policies and historic masonry best practices.
Twelve historic windows underwent a meticulous restoration process, beginning with stripping windows down to the bare wood. Any signs of deterioration were promptly addressed through sash repairs and the installation of new sills where necessary. Sections afflicted by rot underwent dutchman repairs, and to maintain authenticity, historically correct glass was salvaged from another restoration project and installed to match the existing panes. Finally, a precise repaint was executed to blend the restored windows with their surroundings, preserving the architectural heritage.
After obtaining a heritage permit from the City of Kingston, the restoration project commenced with the chipping and repointing of masonry joints. Any deteriorated masonry units were replaced, and limestone units requiring attention were repaired and pinned as necessary. Throughout the restoration process, strict adherence to the heritage restoration policies set forth by the City of Kingston ensured that all work was completed with utmost care and respect for the historical significance of the structure.
2022 – ($230,000)
This project included emergency work on the bell tower to chip and repoint areas of loose joints; some joints and small stone pieces were beginning to fail and fall to the ground at the main entrance. Our work was completed from a 185’ aerial man lift with full pedestrian protection in place below. We then utilized a slightly smaller 150’ articulated boom to perform slate repairs, completed by a heritage roofing sub contractor, as well as installing 36 pins into a buttress where vertical cracking questioned the structural integrity.
The project included the full installation of blue skin A/V barriers, tied into the window jambs, to guarantee a secure seal against external elements. A new CMU base was also installed to provide a solid foundation for further construction. Additionally, new cavity wall insulation was put in place. Following engineered drawings, new brick veneer was installed, ensuring structural integrity and adherence to design requirements.
Dismantle and rebuild of a historical limestone stair case, including the refurbishment of the existing railing, and repairs to the stucco.
Dismantled and rebuilt deteriorated stone areas to ensure the structural integrity of the wall and foundation. In addition, we expertly carried out chip and repoint work on the stone wall below the terrace, seamlessly restoring it to it's original beauty. As a finishing touch, we supplied and installed new Kingston Limestone caps, matched in size and finish to the existing materials.